The major part of the job was completed by the end
    of last week. Gerry, on the left, and Dennis, right,
    are packing up the tools and cleaning the shop now.
    (Dec. 10) Tomorrow will be their last day here.

    An improvement over the 1842 bathroom
    is being installed - December 10.

Milford Daily News photo - December 10 issue.

    Last lunch - December 11. Dennis at end of table,
    Gerry on the right and dehudmidifier guys on the left.

    Installing the dehumidifier. This is a very important part of
    the project, necessary for the survival of books, pictures,
    files and machinery - December 11.

    A meeting to discuss progress and problems of the project has been held each
    Wednesday since the job began. When the weather was warmer they were held at
    the shop, but with the arrival of lower temperatures, they've been at the library. The
    group at the December 12 meeting, shown above, (left to right) includes Tom
    McGovern, Friends of Historic Hopedale, Steve White, Whipple Construction, Dan
    Malloy, Historical Commission and Friends of Historic Hopedale, Phillip Warbasse,
    architect, Chenot Associates, Merrily Sparling, Historical Commission chair and
    Friends of HH, and Gene Phillips, Hopedale town coordinator.
                    
                         
Red Shop Renovation Project - Week 14